Commissioning a Kitchen Before You Own the House
A note on timing, measurement and money when the kitchen has to be ready for the day the removal lorry arrives.
A good part of the work that leaves the Mickfield workshop is destined for houses our clients have not yet moved into. Some are still under offer. Some are in the middle of a survey. Some are a plot with a set of planning drawings and a main contractor about to break ground. In every case the client wants the same thing: to walk into the finished house and find the kitchen already there, tuned to the room, lit, plumbed, working.
That is achievable, but only if the conversation starts earlier than most people expect. This piece sets out how much earlier, what we can decide before you have keys, and how the money is handled when the house is not yet, in the ordinary sense, yours.
The shape of the timeline
From agreed brief to installation, most of our kitchens take 14 to 20 weeks. Before signed drawings there is design and specification, which typically takes 6 to 10 weeks depending on the size of the room, the number of ancillary spaces (scullery, pantry, boot room, wine room) and how quickly the client can settle appliances. Add the two together and the honest figure from first meeting to install is seven to nine months.
That number tends to land differently on different clients. For someone buying a house that already has a serviceable kitchen, nine months is easy. For someone building, it usually maps neatly onto the second-fix window. For someone buying a house that needs work, the answer is almost always: we should have spoken sooner.
Starting the conversation before exchange
For a purchase, the ideal point of contact is once an offer has been accepted and before exchange. That gives us six to eight weeks (often more) to have a first meeting, visit the house, take initial measurements with the vendor’s cooperation, and produce an outline design and a written estimate. Nothing is committed on either side until exchange, but by the time the client owns the house the design work is already underway.
Where the house needs significant work — walls coming out, structural changes, a rear extension — we would rather be introduced at offer stage or earlier. The kitchen shapes the plan more than most rooms; it decides where drainage sits, where the range goes, whether the island can carry a hob or should stay a preparation surface, whether there is room for a scullery behind. Architects who work with us know this. We are happy to sit in on planning conversations at concept stage and hold the brief while the drawings develop.
Building alongside the build
For a new-build or a major renovation with a main contractor already on site, the timing is different again. Here the fixed points are the programme’s dates — first fix, plaster, second fix — and our install has to arrive when the room is ready to receive it. That means we ideally sit down with the client and the architect at the point plans are being finalised, and certainly before first-fix carpentry is drawn.
We work directly with the main contractor from that point on: providing setting-out drawings for stud walls, positions for first-fix plumbing, electrical loads, extract runs, floor build-ups, the lot. It is much cheaper to move a waste pipe on a drawing than to chase it out of a screeded floor.
Measuring a house you do not own
We survey twice before we cut anything — that is covered in its own piece — but the first survey has to happen somehow, and often the client is not yet the legal owner. In practice this is rarely a problem. Vendors are almost always willing to let us in for an hour with a laser and a notepad, particularly once they know a sale is progressing. On a new-build, the architect’s drawings are our starting point, and we visit as soon as the shell is watertight for a proper measured survey.
What we will not do is design off estate-agent floorplans. They are indicative and, in older houses, often wrong by 100mm or more in the places that matter. If there is no way in before exchange, we say so and treat the first proper survey as the point at which layout is confirmed.
Designing for a life not yet lived there
The harder question is not the measurement but the design. How do you decide where the range should go in a room you have never cooked in?
The answer is that you start with the client, not the room. In an early meeting we spend most of the time not talking about the house at all. We talk about how the client already lives: who cooks, when, for how many, what appliances they use every day, what they store, whether the sink is the social heart of the kitchen or a working corner, whether the table is separate or built in. From that we build a set of principles — a working brief — which the design then applies to whichever room is on the drawings.
It is a more disciplined way of working than being led by the space. It also travels well: the same brief can be applied to a slightly different house if the first purchase falls through.
What to lock down, what to defer
Not everything has to be settled early. Some decisions have to be, because they are cut into the building; others can wait until the client has spent time in the room.
Lock down early, before signed drawings:
- layout and cabinet footprint
- appliance schedule (make and model of every appliance, because sizes and service positions vary)
- plumbing positions and waste runs
- electrical loads, socket positions and switching
- extract route and terminal position
- worktop material family (stone, timber, composite) — the structural detail depends on it
Defer, if you want to:
- final paint colour and sheen
- ironmongery finish
- specific worktop stone or timber
- shelf and drawer internal arrangement
- pantry fit-out details
Colour, in particular, is one to hold back. Paint reads differently in a room you have lived in for a fortnight than it does off a sample card in another house. We finish cabinets in the workshop and can lift the final coat on site once the room is decorated, so a colour decision made in month seven costs nothing.
Deposits, stages and a sale that falls through
Our payment structure is a design fee at the outset, a deposit on signature of the manufacturing contract, and staged payments through the build to install. The design fee covers the design and specification work; the deposit covers materials and workshop time.
We recommend the design fee is paid regardless of whether the house purchase completes. There are two reasons. The first is straightforward: the work has been done, and it takes real workshop time and drawing time to do properly. The second is that the drawings are the client’s. If the sale falls through, the design does not die with it. Where the next house is broadly similar in scale and use, the same brief and the same drawings can be adapted, often substantially. Where the next house is very different, at least the working brief carries forward and we start the second design a good deal further on than the first.
The manufacturing deposit is a different matter. We do not take it until contracts on the house have exchanged and drawings are signed. By that point the house is legally the client’s, and the risk of the sale collapsing is behind us.
The drawings are yours
Buying a kitchen before you own the house is not a shortcut. It is a longer conversation, held earlier, with more decisions front-loaded. What it buys is the thing most clients want: a working kitchen on move-in day, not a temporary hob for six months while they wait.
The drawings that come out of it belong to the client, whether the first house completes or not. That, in the end, is what we sell — the thinking, the setting-out, the specification — and then the joinery that is made to it, in the workshop, by the same eight people who drew it.